IAEA GSR Part 2×Operations and Maintenance
Operations & Maintenance in Goals & Plans
Management for safety
What sits here
Goals, strategies and plans are set so that safety is not compromised by other objectives. Business planning, outage planning, decommissioning strategy and funding all belong here, because each can put pressure on safety.
Example documents, by tier
Standard 1
- Outage Management StandardRepresentative exampleStation · addsAlso in ONR Licence Conditions · Periodic shutdownAlso in Process Safety · Asset integrityNot safety case baseline
Process, procedure, work instruction 1
- Periodic Shutdown PlanRepresentative exampleReactor unit · addsAlso in ONR Licence Conditions · Periodic shutdownAlso in Process Safety · Asset integrityNot safety case baseline