Safety Case · How independent assurance of the barriers is arranged
Verification and examination
Purpose
The verification scheme and the well examination scheme, as the safety case describes them. The independent competent person’s role is part of the regulatory basis. The scheme itself, not each examination routine, is what the case relies on.
The question this lens asks
“If this document changed, would the safety case need to be revised and accepted by the competent authority before the change could be made?”
Belongs here
- Verification and examination scheme
- Well examination scheme
Does not belong here
- Individual examination sheets and reports
- Annual assurance reporting
Documents by department (3)
Engineering 2
- STOperational Performance Standards and Verification Examination SchemeRegionIOGP 510 · 02 · EI PSM · 16 · Process Safety · Asset Integrity
- STVerification and Examination SchemeIOGP 510 · 10 · EI PSM · 20 · Process Safety · Asset Integrity
Wells 1
- STWell Examination SchemeIOGP 510 · 10 · EI PSM · 20 · Process Safety · Asset Integrity