Home/Nuclear Power/ONR Licence Conditions
Nuclear Power Generation Company · ONR Licence Conditions

Framework explorer, with document tiers and scope

Each cell is a department × element intersection. Documents are stacked by tier, so the document pyramid appears in every cell. Use the scope selector to see what applies company-wide, at station level or in a single reactor unit. Click a cell to see its documents.

The same 202 documents, seen through ONR Licence Conditions. This is a subset lens: it asks one question of every document and keeps those that answer yes. 148 do; the other 54 are outside it by design and still belong to the management system. Nothing is copied between frameworks: each document is recorded once and carries its position in every framework.

“Does this document form part of the licensee’s arrangements for a licence condition?”

A station: everything company-wide, plus what the station adds.

PO policy · ST standard · PR process, procedure, work instruction · SU supportingCompany-wideStation additionReactor unit additionGuidance: move out
EngineeringOperations & MaintenanceNuclear SafetyRadiological ProtectionHSSEFuel & WasteCommercialFinance & LegalHR / PeopleBusiness Services
02
Marking of the site boundary
03
Control of property transactions
04
Restrictions on nuclear matter on the site
05
Consignment of nuclear matter
06
Documents, records, authorities and certificates
07
Incidents on the site
08
Warning notices
09
Instructions to persons on the site
10
Training
11
Emergency arrangements
12
Duly authorised and other suitably qualified and experienced persons
13
Nuclear safety committee
14
Safety documentation
15
Periodic review
16
Site plans, designs and specifications
17
Management systems
18
Radiological protection
19
Construction or installation of new plant
20
Modification to design of plant under construction
21
Commissioning
22
Modification or experiment on existing plant
23
Operating rules
24
Operating instructions
25
Operational records
26
Control and supervision of operations
27
Safety mechanisms, devices and circuits
28
Examination, inspection, maintenance and testing
29
Duty to carry out tests, inspections and examinations
30
Periodic shutdown
31
Shutdown of specified operations
32
Accumulation of radioactive waste
33
Disposal of radioactive waste
34
Leakage and escape of radioactive material and radioactive waste
35
Decommissioning
36
Organisational capability

35 licence conditions × 10 departments · ONR Standard Licence Conditions

54 documents are not a licence condition arrangement

They answered no to the question above. That is not a gap: a subset lens is only useful if it leaves most of the system out. They remain in the management system and in every integrated framework view.

Show the documents outside this lens
Nuclear Safety 5
  • Nuclear Safety Principles and Decision Making Standard
  • Leadership for Safety Standard
  • Nuclear Safety Culture Assessment
  • Nuclear Safety Performance Indicators
  • Regulator Interface and Licensing Correspondence Procedure
HSSE 11
  • Health, Safety and Environment Policy
  • Conventional Safety Management Standard
  • Fire Safety Management Procedure
  • Environmental Permit Compliance Procedure
  • Environmental Aspects Register
  • Contractor Safety Management Standard
  • Occupational Health Standard
  • Site Security Arrangements Interface Procedure
  • Legal Register
  • Site Stakeholder Engagement Procedure
  • Safety Representatives and Workforce Engagement
Commercial 7
  • Procurement Policy
  • Contractor Management Procedure
  • Grid Code Compliance and Electricity Trading Procedure
  • Contract Performance Review Template
  • Purchase Requisition Form
  • Delegation of Authority: Commercial Commitments
  • Procurement Competence Framework
Finance & Legal 14
  • Anti-Bribery and Corruption Policy
  • Delegation of Authority Standard
  • Decommissioning Funding Arrangements
  • Investment Approval Standard
  • Business Plan and Budget Process
  • Enterprise Risk Management Standard
  • Nuclear Third Party Liability Insurance Procedure
  • Financial Controls Framework
  • Tax Strategy
  • Competition Law Compliance Standard
  • Data Protection Policy
  • Payment Processing Procedure
  • Internal Audit Charter
  • Speak Up Policy
HR / People 10
  • People Policy
  • Recruitment and Selection Procedure
  • Fitness for Duty and Fatigue Management Procedure
  • Drug and Alcohol Policy
  • Absence Management Procedure
  • Disciplinary and Just Culture Policy
  • Grievance Procedure
  • Employee Consultation Procedure
  • Performance Management Process
  • Leadership Development Programme
Business Services 7
  • Information Security Policy
  • Operational Technology Cyber Security Standard
  • Access Management Standard
  • IT Disaster Recovery Plan
  • Business Continuity Plan
  • IT Change Management Procedure
  • Acceptable Use Policy

Representative documents: no source register was available. Titles are built from the ONR licence conditions, IAEA GSR Part 2 and comparable licensed sites, and should be tested against a real register.